Change request assessment

Assesses a project change request against the approved baseline and produces a traceable impact analysis for scope, schedule, cost, quality, risk, resources, and dependencies. Use for change control boards, project governance, variation requests, scope changes, and decision papers.

von adlass TemplatesVersion 1Nutzt adlass-ToolsUniversell

Veröffentlicht 21. Aug. 2026 · Aktualisiert 26. Aug. 2026

Hilfreich · 0Rohes SKILL.md ansehen

Voraussetzungen

Add the project baseline versions, change policy, approval matrix, and estimating conventions. Define the PMO fields and thresholds for cost, schedule, quality, risk, and dependency impact.

Skill-Dokument

Das vollständige SKILL.md, das dein Agent liest und befolgt.

Change request assessment

Purpose

Convert a proposed project change into a decision paper that shows exactly what moves from the approved baseline, what the change costs, what dates or acceptance criteria are affected, and which option is supportable. Keep the requester's wording separate from calculated impact and recommendation.

Scope

Assess one change request using the project charter, requirements baseline, WBS, schedule, cost plan, resource plan, quality plan, risk register, dependency log, and prior approved changes. Cover requested change, rationale, affected deliverables, effort, budget, milestone dates, quality measures, risks, dependencies, and approval route.

Excluded: approving or rejecting the request, editing the master plan, negotiating with the requester, or inventing contingency, cost, duration, or acceptance criteria.

Data basis

  • Change request form, issue or requirement reference, and requester rationale.
  • Approved scope baseline, WBS, schedule, budget, resource allocation, quality criteria, risk register, and dependency log.
  • Change-control policy, approval matrix, and prior change log.

Result

Create an impact sheet with one row per affected deliverable, work package, milestone, cost item, resource, risk, and dependency. Write a decision paper with options, quantified deltas, assumptions, recommendation, approval authority, and unresolved evidence.

Quality criteria

  • Every affected baseline item cites its identifier and source location.
  • Cost, effort, and date deltas show their source values and arithmetic.
  • Scope impact distinguishes added, removed, modified, and unchanged requirements.
  • Recommendation follows the change policy and does not imply approval.
  • Dependencies and risks have an owner or are explicitly recorded as unassigned.

Instructions

Compare the request with the latest approved baseline, then reconcile it against already approved changes. Use the policy's thresholds for approval level, budget variance, milestone slippage, and quality impact; if a threshold is absent, label the assessment as unclassified. Never net unrelated cost lines to hide an increase. Treat a missing baseline as an evidence gap, not as zero. Preserve conflicting estimates side by side and cite the estimating document. State whether each conclusion is fact, calculation, assumption, or recommendation.

Adapt before use

  • Add the project charter, baseline files, change policy, and approval matrix.
  • Define cost, effort, schedule, quality, and risk fields used by the PMO.
  • Set the comparison date when multiple approved baselines exist.
  • Name the decision options and escalation roles accepted by the governance forum.

Verwandte Skills

  • Construction change-order pack

    Builds a documented construction variation package from the change trigger, contract terms, quantities, rates, and time effects. Use for change orders, variation claims, owner instructions, design changes, and subcontractor pricing review.

  • executive document brief

    Creates a source-linked executive document brief deliverable using concrete fields, rules, exceptions, and review controls. Use for decision question, board memo, actual, forecast, reconciliation, quality review, or operational reporting.

  • hr record data quality

    Creates a source-linked hr record data quality deliverable using concrete fields, rules, exceptions, and review controls. Use for employee_id, hire_date, manager_id, duplicate, reconciliation, quality review, or operational reporting.

  • invoice intake coding

    Creates a source-linked invoice intake coding deliverable using concrete fields, rules, exceptions, and review controls. Use for invoice_number, PO, receipt, GL account, reconciliation, quality review, or operational reporting.