Program dependency and milestone map
Consolidates project milestones into a program dependency map showing predecessor links, shared-resource collisions, critical-path exposure, and the effect of date changes. Use for PMO planning, portfolio reviews, delivery-risk analysis, or milestone governance.
Veröffentlicht 21. Aug. 2026 · Aktualisiert 26. Aug. 2026
Voraussetzungen
Map milestone and dependency fields. provide resource-calendar conventions. define the program horizon and delay scenarios.
Skill-Dokument
Das vollständige SKILL.md, das dein Agent liest und befolgt.
Program dependency and milestone map
Purpose
Combine project schedules into one traceable view of milestone order, cross-project dependencies, shared resources, and delay consequences.
Scope
Use project plans, milestone registers, dependency logs, RAID logs, resource allocations, release calendars, and approved program dates. Assess predecessor, successor, owner, resource, baseline date, forecast date, and status.
Excluded: replanning schedules, assigning people, approving scope changes, or declaring a project late without a dated baseline.
Data basis
- Milestone table with project_id, milestone_id, name, owner, baseline_date, forecast_date, status, and resource.
- Dependency table with predecessor_id, successor_id, dependency_type, lag, and source.
- Resource allocation, release calendar, RAID log, and program charter.
Result
A milestone map, dependency register, collision table, and concise program risk brief with dates, owners, delay scenarios, and citations.
Quality criteria
- Every milestone has one project and a baseline or explicit baseline-missing flag.
- Dependency links resolve to existing milestone IDs or are exceptions.
- Forecast variance is calculated consistently and negative lags are preserved.
- Shared-resource collisions name the resource and overlapping date windows.
- Any critical-path claim cites the schedule rule or source dependency chain.
Instructions
Normalize dates to the program calendar while retaining source dates and timezone. Classify links as finish-to-start, start-to-start, finish-to-finish, or unspecified. Flag cycles and orphan links before calculating downstream effects. For a delay scenario, add the delay to successors only when the dependency type and lag support it; label all other effects as qualitative. Keep baseline, forecast, and scenario dates separate.
Adapt before use
The map should make a date collision visible even when no owner has yet accepted the resulting delivery risk.
- Map project, milestone, dependency, resource, and schedule columns.
- Set calendar, working-day, lag, variance, collision, and critical-path rules.
- Add the program charter, release calendar, and approved scenario delay size.
Verwandte Skills
- Change request assessment
Assesses a project change request against the approved baseline and produces a traceable impact analysis for scope, schedule, cost, quality, risk, resources, and dependencies. Use for change control boards, project governance, variation requests, scope changes, and decision papers.
- Construction change-order pack
Builds a documented construction variation package from the change trigger, contract terms, quantities, rates, and time effects. Use for change orders, variation claims, owner instructions, design changes, and subcontractor pricing review.
- executive document brief
Creates a source-linked executive document brief deliverable using concrete fields, rules, exceptions, and review controls. Use for decision question, board memo, actual, forecast, reconciliation, quality review, or operational reporting.
- hr record data quality
Creates a source-linked hr record data quality deliverable using concrete fields, rules, exceptions, and review controls. Use for employee_id, hire_date, manager_id, duplicate, reconciliation, quality review, or operational reporting.